Lead Local Flood Authority planning application advice service

You can get paid advice from the Lead Local Flood Authority about managing surface water and designing sustainable drainage systems (SuDS) for major development proposals.

Why use this service

  • Identify potential surface water issues with your proposed development early

  • Get advice on the surface water parts of your flood risk assessment and drainage strategy

  • Receive guidance to help you comply with national policy, guidance, and standards, including the National Standards for Sustainable Drainage Systems (SuDS)

  • Where needed, get advice about ordinary watercourse consent requirements for your development

When to use this service

  • Before submitting a major planning application with surface water drainage

  • To address issues raised by the Lead Local Flood Authority on live applications, for example if your proposal has received an objection about surface water flood risk or drainage

  • To help with the discharge of conditions recommended by the Lead Local Flood Authority

Using this service helps you submit a stronger application and reduces the risk of an objection from the Lead Local Flood Authority.

How to use the service

  • Complete the application form and prepare your supporting evidence

  • Email your application and evidence to suds@lancashire.gov.uk or send them by post

  • If your application is valid, you will receive an invoice for payment

  • After payment, we will contact you to arrange a technical meeting

  • Following the meeting, we will send written advice summarising the key points within the timescales set out in our Terms of Service

Cost and timescales

The cost depends on your site area and which service you choose (standard or fast track).

Site area and fees

Site area

Standard fee

Fast track fee

Small site: Up to and including 1 ha

£1,140.00

£1,368.00

Medium site: 1.01 ha to 2 ha

£1,500.00

£1,800.00

Large site: 2.01 ha to 10 ha

£2,210.00

£2,652.00

Strategic site: More than 10.01 ha

£3,280.00

£3,936.00

Indicative timescales

Service

Technical meeting duration

Meeting held within

Written advice issued within

Standard

Up to 2 hours

28 days of payment

7 days of meeting

Fast track

Up to 2 hours

14 days of payment

7 days of meeting