A6070 Carnforth proposed road closures

There will be traffic restrictions in place to provide working space and to protect the workforce as follows.

June 2024 – mid July 2024

A601(M) / A6070 Lane 2 Closure East and Westbound
(Lane 1 Open with temporary 40mph speed limit.)

Mid July 2024 – February 2025

A601(M) / A6070 Lane 1 or Lane 2 Closure East and Westbound as required by the works.  (*)
(One lane will remain open with temporary 40mph speed limit.)

Mid July 2024 – February 2025

Closure of Higher North Road at the Bridge.
(Pedestrian access to be maintained.)

February 2025- March 2025

Several night time closures during this period.
Exact dates and times of closures and diversion routes for traffic will be publicised well in advance.
(Diversion routes will be signed.)

(*) Some night time closures may be required during this period.  Exact dates and times of closures and diversion routes for traffic will be publicised well in advance. (Diversion routes will be signed.)