Construction schedule
There is a lot of preparatory work required before works start on site, however, the current programme of works comprise:
April 24 – May 24
Hard shoulder works
(New verge construction, drainage, safety fencing)
June 24 – mid July 24
Central Reserve
(Kerbing, drainage, safety fencing)
Mid July 24 – February 25
Higher North Road Bridge
(Concrete repairs and bearing replacement)
October 24 – February 25
Elpha Bridge
(Concrete repairs and parapet replacement)
October 24 – February 25
Brewers Barn East Bridge
(Concrete repairs, bearing replacement and parapet replacement)
October 24 – February 25
Brewers Barn West Bridge
(Concrete repairs, bearing replacement and parapet replacement)
February 25- March 25
Highway Repairs
(Carriageway Resurfacing, road marking and signs)