Table 3.3
|
Lancashire LTP2 Programme 2006/07-2010/11 Bus and Rail Improvements |
Forecast Total Cost | Forecast Partner Contributions | Provisional LTP Resources |
2006 |
2007 | 2008 | 2009 | 2010 | |
| Project | £,000 | £,000 | £,000 |
£,000 |
£,000 | £,000 | £,000 | £,000 | |
| Chorley Connect | Chorley | 200 | 200 | 200 | |||||
| Civitas Sustainable Transport Project | Preston | 800 | 200 | 600 | 200 | 200 | 200 | 200 | |
| South Fylde Community Rail Schemes | Fylde | 300 | 300 | 100 | 200 | ||||
| Community Rail Infrastructure | All | 500 | 500 | 100 | 100 | 100 | 100 | 100 | |
| Quality Bus - Bus Stop Improvements | All | 3000 | 3000 | 1000 | 500 | 500 | 500 | 500 | |
| Bus Priority Measures | All | 1500 | 1500 | 500 | 250 | 250 | 250 | 250 | |
| East Lancashire Rapid Transit Development | Hyndburn | 300 | 300 | 100 | 100 | 100 | |||
| Rawtenstall Interchange | Rossendale | 3500 | 3500 | 2000 | 1500 | ||||
| Bamber Bridge Public Transport Initiatives | South Ribble | 200 | 200 | 100 | 100 | ||||
| Buckshaw Railway Station and Park & Ride | Chorley | 2700 | 2700 | 0 | 1500 | 1200 | |||
| Quality Bus - Wigan to Southport | West Lancashire | 700 | 700 | 200 | 200 | 200 | 100 | ||
| Ribble Valley Rural Transport Infrastructure | Ribble Valley | 300 | 300 | 100 | 100 | 100 | |||
| Pendle Public Transport Improvements | Pendle | 300 | 300 | 50 | 150 | 100 | |||
| Quality Bus -Nelson to Manchester | Pendle Burnley Rossendale |
400 | 400 | 250 | 150 | ||||
| Preston Public Transport Interchange | Preston | 4400 | 4400 | 50 | 1350 | 3000 | |||
| Nelson Interchange | Pendle | 3500 | 3500 | 200 | 1800 | 1500 | |||
| Cleveleys Bus-Tram Interchange | Wyre | 1000 | 1000 | 500 | 500 | ||||
| Quality Bus -St Annes to Fleetwood | Fylde/Wyre | 600 | 600 | 200 | 200 | 200 | |||
| Accrington Interchange | Hyndburn | 2700 | 2700 | 1500 | 1200 | ||||
| Community Rail Improvements West lancashire | West Lancashire | 300 | 300 | 200 | 100 | ||||
| Blackpool to Fleetwood Tramway | Wyre | 1600 | 1600 | 800 | 800 | ||||
| Ormskirk Interchange Improvements | West Lancashire | 1200 | 1000 | 1000 | |||||
| Other Partner Contributions | 4600 | -4600 | |||||||
| Ormskirk Interchange Phase 2 | West Lancashire | 250 | 250 | 250 | |||||
| Cleveleys Bus Tram Interchange Phase 2 | Wyre | 900 | 900 | 900 | |||||
| Smartcard scheme extension | All | 750 | 750 | 50 | 200 | 200 | 200 | 100 | |
| Community Rail station improvements | All | 1100 | 1100 | 100 | 250 | 250 | 250 | 250 | |
| Extension of Lancashire Real Time System | All | 1750 | 1750 | 200 | 500 | 500 | 500 | 50 | |
| East Lancashire Quality Bus Routes | Hyndburn Burnley Pendle |
800 | 800 | 100 | 200 | 500 | |||
| Total Public Transport (Base schemes) |
30000 | 7500 | 22300 | 4200 | 5050 | 3500 | 7800 | 10800 | |
| Total Public Transport (+10%schemes) | 33000 | 7500 | 25300 | 4350 | 5500 | 3950 | 8250 | 10800 | |
| Total Public Transport (+25% schemes) |
35550 | 7500 | 27850 | 4650 | 6200 | 4950 | 8750 | 10800 |
| Lancashire LTP2 Programme 2006/07-2010/11 Accessibility, Information |
Forecast Total Cost | Forecast Partner Contributions | Provisional LTP Resources | 2006/07 | 2007/08 | 2008/09 | 2009/10 | 2010/11 | |
| Projects | £,000 | £,000 | £,000 | £,000 | £,000 | £,000 | £,000 | £,000 | |
| Building Schools for the Future - Transport Links | Burnley | 200 | 200 | 50 | 50 | 50 | 50 | ||
| Civitas Preston Bus Information | Preston/South Ribble | 450 | 150 | 300 | 150 | 150 | 100 | 50 | |
| Towneley Improvement Zone | Burnley | 250 | 250 | 100 | 50 | 100 | |||
| Civitas Personalised Travel Planning | Preston | 600 | 200 | 400 | 200 | 200 | 200 | ||
| Ribble Valley Multi Modal Transport Study | Ribble Valley | 100 | 100 | 50 | 50 | ||||
| Chorley Pathfinder for Accessibility | Chorley | 100 | 100 | 50 | 50 | ||||
| Ormskirk Traffic and Parking Management | West Lancashire | 250 | 250 | 100 | 100 | 50 | |||
| Personalised Travel Planning in Lancaster | Lancaster | 600 | 600 | 200 | 200 | 200 | |||
| Accessibility Projects | All | 1500 | 1500 | 300 | 300 | 300 | 300 | 300 | |
| Smartcard and Ticketing Development | All | 1750 | 1750 | 350 | 350 | 350 | 350 | 350 | |
| Travel Information Systems | All | 1250 | 1250 | 250 | 250 | 250 | 250 | 250 | |
| Parking Management | All | 500 | 500 | 100 | 100 | 100 | 100 | 100 | |
| School Travel Planning Programme | All | 1000 | 1000 | 200 | 200 | 200 | 200 | 200 | |
| Business Travel Plans Programme | All | 500 | 500 | 100 | 100 | 100 | 100 | 100 | |
| Street Lighting Crime Reduction | All | 600 | 600 | 200 | 100 | 100 | 100 | 100 | |
| Controlled Crossings Access Programme. | All | 500 | 500 | 100 | 100 | 100 | 100 | 100 | |
| Community Links in Ribble Valley | Ribble Valley | 200 | 200 | 100 | 100 | ||||
| Personalised Travel Planning | All | 900 | 900 | 300 | 300 | 300 | |||
| Accessibility Improvements to Employment Areas | South Ribble | 350 | 350 | 150 | 100 | 100 | |||
| Park & Ride, Cycle, Walk in Rossendale | Rossendale | 600 | 600 | 300 | 300 | ||||
| Other Partner Contributions | 850 | -850 | |||||||
| Town Centre Signing and Security | All | 200 | 200 | 40 | 40 | 40 | 40 | 40 | |
| Asset Management Plan and Ped Improvements | Ribble Valley | 600 | 600 | 50 | 150 | 150 | 150 | 100 | |
| Accessibility Improvements to Employment Areas | All | 420 | 420 | 50 | 100 | 100 | 100 | 70 | |
| School Travel Plan Scheme Extensions | All | 725 | 725 | 200 | 200 | 150 | 100 | 75 | |
| Interchange Enhanced Signage | All | 1100 | 1100 | 250 | 250 | 250 | 350 | 250 | |
| Total Accessibility (Base schemes) |
12200 | 1200 | 11000 | 2500 | 2450 | 3440 | 3040 | 2735 | |
| Total Accessibility (+10% schemes) |
13420 | 1200 | 12220 | 2640 | 2740 | 3440 | 3040 | 2735 | |
| Total Accessibility (+25% schemes) |
15245 | 1200 | 14045 | 3090 | 3190 | 3440 | 3040 | 2735 |
| Lancashire LTP2 Programme 2006/07-2010/11 Active Travel |
Forecast Total Cost | Forecast Partner Contrib- utions |
Provisional LTP Resources | 2006 | 2007 | 2008 | 2009 | 2010 | |
| Projects | £,000 |
£,000 |
£,000 |
£,000 |
£,000 |
£,000 |
£,000 |
£,000 |
|
| Lancaster Cycling Demonstration Town Project | Lancaster | 500 | 500 | 250 | 250 | ||||
| Chorley Pedestrian Priority, Access and Parking | Chorley | 300 | 300 | 100 | 200 | ||||
| Morecambe West End Neighbourhood Schemes | Lancaster | 300 | 300 | 100 | 150 | 50 | |||
| Blackpool Airport Ground Access | Fylde | 350 | 350 | 100 | 100 | 100 | 50 | ||
| Accrington Footpaths and Signing | Hyndburn | 350 | 350 | 50 | 100 | 100 | 100 | ||
| School Travel Plans Programme in South Ribble | South Ribble | 250 | 250 | 50 | 50 | 50 | 50 | 50 | |
| Guild Wheel Cycling Project | Preston | 500 | 500 | 100 | 100 | 100 | 100 | 100 | |
| Active Travel in Ribble Valley | Ribble Valley | 500 | 500 | 100 | 100 | 100 | 100 | 100 | |
| Cycling Package Ormskirk and Skelmersdale | West Lancashire | 500 | 500 | 100 | 100 | 100 | 100 | 100 | |
| West Accrington/Church Housing Market Renewal | Hyndburn | 346 | 346 | 100 | 100 | 96 | 50 | ||
| Countryside Access in Ribble Valley | Ribble Valley | 400 | 400 | 50 | 50 | 100 | 100 | 100 | |
| Elevate Housing Market Renewal Transport Links | Burnley | 2000 | 2000 | 100 | 500 | 500 | 500 | 400 | |
| Whitefield and Bradley Housing Market Renewal | Pendle | 350 | 350 | 200 | 150 | ||||
| Rossendale Active Travel Network | Rossendale | 300 | 300 | 60 | 60 | 60 | 60 | 60 | |
| 20mph Zones Programme | All | 1750 | 1750 | 350 | 350 | 350 | 350 | 350 | |
| Cycle Schemes Programme | All | 2500 | 2500 | 500 | 500 | 500 | 500 | 500 | |
| Burnley Cycling and Walking Projects | Burnley | 600 | 600 | 100 | 150 | 150 | 100 | 100 | |
| Pendle Cycling and Pedestrian Access | Pendle | 300 | 300 | 100 | 200 | ||||
| Promoting Cycling Package in Fylde | Fylde | 300 | 300 | 150 | 150 | ||||
| Wyre Rail and Cycle Partnership | Wyre | 500 | 500 | 200 | 300 | ||||
| Other Partner Contributions | All | 1800 | -1800 | ||||||
| Heysham Pedestrian & Cyclist Improvements | Lancaster | 350 | 350 | 50 | 100 | 100 | 100 | ||
| Bike Aid and Bike Local | All | 250 | 250 | 50 | 50 | 50 | 50 | 50 | |
| Clearzone Pedestrian Scheme in Preston | Preston | 550 | 550 | 200 | 200 | 150 | |||
| Pedestrian and Cycling Access Improvements | All | 1500 | 1500 | 300 | 300 | 300 | 300 | 300 | |
| Rawtenstall Pedestrian Access | Rossendale | 400 | 400 | 150 | 250 | ||||
| Wyre Pedestrian Improvement Plan | Wyre | 300 | 300 | 100 | 200 | ||||
| Total Active Travel (Base schemes) |
12896 | 1800 | 11096 | 2210 | 3160 | 2706 | 2610 | 2410 | |
| Total Active Travel (+10% schemes) |
14046 | 1800 | 12246 | 2460 | 3460 | 3006 | 2660 | 2460 | |
| Total Active Travel (+25% schemes) |
16246 | 1800 | 14446 | 2760 | 3760 | 3456 | 3310 | 2960 |
| Lancashire LTP2 Programme 2006/07-2010/11 Highway Management |
Forecast Total Cost | Forecast Partner Contrib- utions |
Provisional LTP Resources | 2006 | 2007 | 2008 | 2009 | 2010 | |
| Projects | £,000 | £,000 | £,000 | £,000 | £,000 | £,000 | £,000 | £,000 | |
| Access to ROF Regional Investment Site | Chorley | 1750 | 1750 | 0 | 1000 | 750 | |||
| Huncoat Waste Technology Park Access | Hyndburn | 6000 | 6000 | 0 | 3000 | 3000 | |||
| Heysham to M6 Link Design and Preparation | Lancaster | 1000 | 1000 | 200 | 800 | ||||
| Ormskirk Bypass Major Scheme Development | West Lancashire | 400 | 400 | 200 | 100 | 100 | |||
| Huncoat -Whinney Hill Scheme Development | Hyndburn | 150 | 150 | 50 | 50 | 50 | |||
| Safer Burnley | Burnley | 350 | 350 | 100 | 100 | 100 | 50 | ||
| Transport Planning for Whitebirk Regional Site | Hyndburn | 200 | 200 | 100 | 50 | 50 | |||
| Eaves Green Link Road | Chorley | 8632 | 6216 | 2416 | 2400 | 4092 | 2140 | ||
| UTMC | All | 2000 | 2000 | 400 | 400 | 400 | 400 | 400 | |
| Tardy Gate AQMA Action Plan | South Ribble | 300 | 300 | 50 | 100 | 100 | 50 | ||
| North East Preston Park and Ride Sites | Preston | 3500 | 3500 | 50 | 50 | 1000 | 1200 | 1200 | |
| Preston Air Quality Junction Improvements | Preston | 250 | 250 | 50 | 200 | ||||
| Minor Junction Improvememts | All | 2500 | 2500 | 500 | 500 | 500 | 500 | 500 | |
| Lancaster AQMA Low Emission Zone | Lancaster | 800 | 800 | 20 | 20 | 10 | 350 | 400 | |
| Local Safety Scheme Programme | All | 5000 | 5000 | 1000 | 1000 | 1000 | 1000 | 1000 | |
| A681 Congestion Reduction Measures | Rossendale | 550 | 550 | 150 | 0 | 0 | 200 | 200 | |
| Fylde Coast Sub-Regional Proposals for A585 | Fylde/Wyre | 150 | 150 | 50 | 0 | 0 | 50 | 50 | |
| Broughton A6/M55 Congestion Reduction | Preston | 14500 | 10250 | 4250 | 100 | 150 | 7000 | 6000 | 1250 |
| Leyland Town Centre Regeneration | South Ribble | 500 | 500 | 50 | 250 | 200 | |||
| Clayton-le-Moors Area Package | Hyndburn | 350 | 350 | 100 | 100 | 100 | 50 | ||
| A56 Villages Bypass Development Work | Pendle | 200 | 200 | 50 | 50 | 100 | |||
| Britannia Junction Improvement | Hyndburn | 800 | 800 | 100 | 400 | 300 | |||
| Forecast Partner Contributions | All | 4000 | -4000 | ||||||
| Fylde Coast Sub-Regional Proposals Phase 2 | Fylde/Wyre | 1750 | 1750 | 250 | 200 | 800 | 250 | 250 | |
| Congestion Reduction Junction Improvements | All | 500 | 500 | 100 | 100 | 100 | 100 | 100 | |
| Preston/South Ribble Park & Ride | Preston | 3240 | 3240 | 140 | 500 | 1100 | 1000 | 500 | |
| Total Highway Management (Base schemes) |
49882 | 28216 | 21666 | 9420 | 11512 | 13850 | 10900 | 5450 | |
| Total Highway Management (+10% schemes) |
52132 | 23916 | 9770 | 11812 | 13850 | 10900 | 5800 | ||
| Total Highway Management (+25% schemes) |
55372 | 27156 | 9910 | 12312 | 14950 | 11900 | 6300 | ||
| Total Programme | 104978 | 38716 | 66062 | 18330 | 22172 | 23496 | 24350 | 21395 | |
| LTP Provisional Allocation | 66062 | 12879 | 11613 | 12682 | 13829 | 15059 | |||
| Forecast Partner Contributions | 43681 | 5451 | 10559 | 10814 | 10521 | 6336 | |||
| LTP Provisional Allocation (+10% ) |
72668 | 20163 | 24389 | 25846 | 26785 | 23535 | |||
| LTP Provisional Allocation (+25%) |
82578 | 22913 | 27715 | 29370 | 30438 | 26744 |
3.3.1 Allocation of Additional Block Funding
Lancashire has a base block funding allocation of £660 million over the period of the LTP2. We are required to show what additional schemes we would deliver in our LTP2 if we secured additional funding of 25%. As an integrated part of our Risk Management Strategy, the monitoring framework associated with the LTP and our departmental management structure, we have selected addition schemes which are lower priority, but which are important to our continuing to deliver excellent transport to the people of Lancashire. These additional schemes, above the base funding figure, have also been prioritised using our scoring system as described in Section 3.2. We have placed them in two categories above the ‘base funding’ showing which schemes will be delivered if we are awarded an additional 10% or 25% funding (see the following tables).Table 3.3.1a
|
Funding Category |
£ (million) |
|
Base |
660 |
|
+10% |
726 |
|
+25% |
826 |
Table 3.3.1b Additional Public Transport Schemes
Additional 10% Allocation |
||